Hydropower in the Mekong River Basin

The estimated hydropower potential of Mekong River Basin about 58,930 Megawatts (MW).[1][2][3] As of February 2024, there are an estimated 167 Hydropower Plants (HPPs) in the Mekong, with a combined installed capacity of some 36,376.3 MW. An additional 20 HPPs are currently under construction and at various stages of completion. These have a combined installed capacity of an additional 4,535.5 MW.

The single most significant impact on the use of water and its management in the Mekong Region is hydropower.[4] These developments in the Mekong River Basin have resulted in substantial environmental and social impacts, which are summarised below. These have fuelled controversy [5] and hydropower is a prominent part of the discussion around the river, its basin, and its management. This debate occurs in both the academic literature, as well as the media, and is a focus for many activist groups.[6][7]

The countries that share the Mekong River Basin have all sought the large-scale infrastructural development of its waters. As part of China's Great Western Development program, large-scale hydropower development in China's Yunnan Province has been substantial,[8][9][10] on the Mekong, the Jinsha, and the Red rivers. Large amounts of Yunnan's hydropower is exported eastwards to energy intensive load centres, such as Guangxi and Guangdong.[11] Yunnan, however, has large electricity over-supply problems, which has led to significant hydropower curtailment.[11][12]

The Lao government has also prioritized hydropower development, primarily as an export commodity. In 2021, almost 82% of Lao electricity was exported, mostly to Thailand.[13] Power production (from all sources, including hydropower) contributed 12.8% to national GDP in 2022, while electricity exports comprised almost 29% of total export values in the same year,[14] and investments in electricity production represented 79% of total foreign direct investment in 2021.[15]

Most of Cambodia's hydropower has been developed in the southwest of the country, outside of the Mekong River Basin.[16][17] Its largest HPP, the Lower Sesan 2 is, however, within the Mekong River Basin, and generates some 20% of the country's electricity.[18] Cambodia has ruled out developing hydropower on the Mekong mainstream,[19] but multiple dams are planned for construction in Mekong tributary catchments. Cambodia also exports electricity directly from the Don Sahong HPP, a southern Lao dam located on the Mekong mainstream.[20]

In Thailand, little technically exploitable hydropower potential remains in its parts of the Mekong River Basin. Most of its HPPs were developed in the 1980s and 1990s, and accompanied by large-scale irrigation infrastructure development as part of the massive Kong-Chi-Mun Project,[21] more recently rearticulated as the Khong-Loei-Chi-Mun Project [22][23] Large-scale energy infrastructure in Thailand has been met with strong resistance - for example, the Assembly of the Poor's opposition to the Pak Mun HPP, the last dam to be commissioned in Thailand. This has forced Thailand to export the social and environmental externalities of hydropower construction and operation to neighbouring states.[24][25]

While there are multiple HPPs planned for Myanmar parts of the Mekong River Basin,[26] years of political instability have generally impended hydropower development.

Vietnam's Mekong hydropower development is concentrated in its Central Highlands. It does not appear as if any technically-exploitable hydropower potential remains. Here, hydropower has also been accompanied by significant irrigation development. Vietnam's hydropower investments in this area includes sizeable dams on two key Mekong tributaries, the Sesan and the Srepok rivers.

Mekong mainstream hydropower plants

HPPs on the Mekong mainstream have aroused particular environmental concerns.[27][28] The majority of these are based in China's Yunnan Province. Table 1 below indicates the status of each of these HPPs.

Table 1: Hydropower plants on the Mekong mainstream[29]

ProjectCountryLocationCODInstalled capacity (MW)Status
Sambor12.786849°N 105.938582°E / 12.786849; 105.938582 (Sambor HPP)N/A2,600Cancelled
Stung Treng13.575317°N 105.98345°E / 13.575317; 105.98345 (Stung Treng HPP)N/A980Cancelled
Angsai32.466805°N 95.394246°E / 32.466805; 95.394246 (Angsai HPP) ?55Planned
Baita28.980898°N 98.626669°E / 28.980898; 98.626669 (Baita HPP) ? ?Planned
Banda30.2°N 97.93365°E / 30.2; 97.93365 (Banda HPP) ?1,000Planned
Bangduo29.469708°N 98.394729°E / 29.469708; 98.394729 (Bangduo HPP) ?720Planned
Dachaoshan24.024947°N 100.3703°E / 24.024947; 100.3703 (Dachaoshan HPP)20031,350Commissioned
Dahuaqiao26.308096°N 99.139288°E / 26.308096; 99.139288 (Dahuaqiao HPP)2018920Commissioned
Dongzhong31.872777°N 96.99°E / 31.872777; 96.99 (Dahuaqiao HPP) ?108Planned
Ganlanba21.843867°N 100.937917°E / 21.843867; 100.937917 (Ganlanba HPP) ?155Planned
Gongguoqiao25.585917°N 99.335567°E / 25.585917; 99.335567 (Gongguoqiao HPP)2012900Commissioned
Guoduo31.529089°N 97.191279°E / 31.529089; 97.191279 (Guoduo HPP)2015160Commissioned
Guonian28.319211°N 98.868424°E / 28.319211; 98.868424 (Guonian HPP)N/A1,200Cancelled
Gushui28.608683°N 98.746133°E / 28.608683; 98.746133 (Gushui HPP) ?2,600Planned
Huangdeng26.548199°N 99.112669°E / 26.548199; 99.112669 (Huangdeng HPP)20171,900Commissioned
Jinghong22.053206°N 100.766478°E / 22.053206; 100.766478 (Jinghong HPP)20091,750Commissioned
Lidi27.848016°N 99.030555°E / 27.848016; 99.030555 (Lidi HPP)2019420Commissioned
Lin Chang31.1804°N 97.1852°E / 31.1804; 97.1852 (Lin Chang HPP) ?72Planned
Longqingxia32.884167°N 95.350283°E / 32.884167; 95.350283 (Longqingxia HPP)20062.5Commissioned
Manwan24.622086°N 100.448544°E / 24.622086; 100.448544 (Manwan HPP)19951,570Commissioned
Mengsong21.780267°N 101.147367°E / 21.780267; 101.147367 (Mengsong HPP)N/A600Cancelled
Miaowei25.854121°N 99.163155°E / 25.854121; 99.163155 (Miaowei HPP)20171,400Commissioned
Nuozhadu22.642128°N 100.436336°E / 22.642128; 100.436336 (Nuozhadu HPP)20145,850Commissioned
Quzika30.039854°N 97.889503°E / 30.039854; 97.889503 (Quzika HPP) ?405Planned
Ru Mei29.649933°N 98.3477°E / 29.649933; 98.3477 (Ru Mei HPP) ?2,100Planned
Sidige30.985°N 97.339°E / 30.985; 97.339 (Cege HPP) ?129Planned
Tuoba27.194231°N 99.107516°E / 27.194231; 99.107516 (Tuoba HPP)20241,400Commissioned
Wunonglong27.932554°N 98.9333°E / 27.932554; 98.9333 (Wunonglong HPP)2018990Commissioned
Xiaowan24.7042226°N 100.091255°E / 24.7042226; 100.091255 (Xiaowan HPP)20104,200Commissioned
Yue Long30.868008°N 97.347124°E / 30.868008; 97.347124 (Yue Long HPP)2030100Planned
Ban Koum15.417881°N 105.587364°E / 15.417881; 105.587364 (Ban Koum HPP)20301,872Planned
Don Sahong13.956223°N 105.964247°E / 13.956223; 105.964247 (Don Sahong HPP)2020240Commissioned
Luang Prabang20.06663°N 102.192339°E / 20.06663; 102.192339 (Luang Prabang HPP)20301,460Under construction
Pak Chom18.201038°N 102.050588°E / 18.201038; 102.050588 (Pak Chom HPP) ?1,079Planned
Pak Beng19.849455°N 101.019507°E / 19.849455; 101.019507 (Pak Beng HPP)2033912Planned
Pak Lay18.401361°N 101.58362°E / 18.401361; 101.58362 (Pak Lay HPP)2029728Planned
Phoug Noi15.050186°N 105.848498°E / 15.050186; 105.848498 (Phoug Noi HPP)2029728Planned
Sanakham17.829183°N 101.556969°E / 17.829183; 101.556969 (Sanakham HPP)2028684Planned
Thako13.959072°N 105.988047°E / 13.959072; 105.988047 (Thako HPP)N/A86-172Cancelled
Xayaburi19.254006°N 101.813699°E / 19.254006; 101.813699 (Xayaburi HPP)20191,285Commissioned

Notes: COD = Commercial Operating Date; N/A = Not Applicable

Existing hydropower infrastructure in the Mekong River Basin

Table 2: Commissioned dams in the Mekong River Basin (15 MW installed capacity and above)[29]

ProjectCountryRiverLocationCODInstalled capacity (MW)Mean Annual Energy (GWh)Height (m)Crest length (m)Total storage (million m3)Max reservoir area (km2)
Lower Sesan 2Sesan13.551408°N 106.263841°E / 13.551408; 106.263841 (Lower Sesan 2 HPP)20184002,312457,7291,790335
DachaoshanMekong24.024947°N 100.3703°E / 24.024947; 100.3703 (Dachaoshan HPP)20031,3505,50011548189026.25
DahuaqiaoMekong26.308096°N 99.139288°E / 26.308096; 99.139288 (Dahuaqiao HPP)20189204,070106231.5293
GanlanbaMekong21.843867°N 100.937917°E / 21.843867; 100.937917 (Ganlanba HPP)20151551,17760.545857758
GongguoqiaoMekong25.585917°N 99.335567°E / 25.585917; 99.335567 (Gongguoqiao HPP)20129004,041105356316343
GuoduoMekong31.529089°N 97.191279°E / 31.529089; 97.191279 (Guoduo HPP)201516082393235.583
HuangdengMekong26.548199°N 99.112669°E / 26.548199; 99.112669 (Huangdeng HPP)20171,9008,5782034571,613
JinfengNan La He21.592026°N 101.225135°E / 21.592026; 101.225135 (Jinfeng HPP)19981664.34519.48
JinghongMekong22.053206°N 100.766478°E / 22.053206; 100.766478 (Jinghong HPP)20091,7505,570108705.51,140510
JinheJin He30.806181°N 97.332926°E / 30.806181; 97.332926 (Jinhe HPP)2004603673468.44.27
LaoyinyanGua Lan Zi He/Shun Dian He24.469128°N 99.81754°E / 24.469128; 99.81754 (Laoyinyan HPP)1997164.21,092
LidiMekong27.848016°N 99.030555°E / 27.848016; 99.030555 (Lidi HPP)20194201,75375346.4753.7
Luozhahe 1Luo Zha He24.505207°N 100.451749°E / 24.505207; 100.451749 (Luozhahe 1 HPP)2018301355914.33
Luozhahe 2Luo Zha He24.486867°N 100.402128°E / 24.486867; 100.402128 (Luozhahe 2 HPP)2016{50225713,391
ManwanMekong24.622086°N 100.448544°E / 24.622086; 100.448544 (Manwan HPP)19951,5706,710132418920415
MiaoweiMekong25.854121°N 99.163155°E / 25.854121; 99.163155 (Miaowei HPP)20171,4005,999140660
Nanhe 1Luo Zha He24.342442°N 100.012183°E / 24.342442; 100.012183 (Nanhe 1 HPP)20094017056.814811.36
Nanhe 2Luo Zha He24.377086°N 100.050098°E / 24.377086; 100.050098 (Nanhe 2 HPP) ?25100
NuozhaduMekong22.642128°N 100.436336°E / 22.642128; 100.436336 (Nuozhadu HPP)20145,85023,91226260823,703320
TuobaMekong27.194231°N 99.107516°E / 27.194231; 99.107516 (Tuoba HPP)20241,400Commissioned
WunonglongMekong27.932554°N 98.9333°E / 27.932554; 98.9333 (Wunonglong HPP)20189904,116138247284
XiaowanMekong24.7042226°N 100.091255°E / 24.7042226; 100.091255 (Xiaowan HPP)20104,20018,99029589314,560194
Xi'er He 1Xi'er He25.578801°N 100.202419°E / 25.578801; 100.202419 (Xi'er He 1 HPP)1979105440
Xi'er He 2Xi'er He25.561991°N 100.131191°E / 25.561991; 100.131191 (Xi'er He 2 HPP)198750371220.2
Xi'er He 3Xi'er He25.558584°N 100.107878°E / 25.558584; 100.107878 (Xi'er He 3 HPP)19885022321
Xi'er He 4Xi'er He25.576262°N 100.065574°E / 25.576262; 100.065574 (Xi'er He 4 HPP)19715014
XunCunHei Hui Jiang25.421835°N 99.993301°E / 25.421835; 99.993301 (XunCun HPP)1999783456716574
Mong WaNam Lwe21.396967°N 100.32584°E / 21.396967; 100.32584 (Mong Wa HPP)201766330.4551788.01
Don SahongMekong13.956223°N 105.964247°E / 13.956223; 105.964247 (Don Sahong HPP)20202402,000256,800252.2
Houay HoHouayho/Xekong15.059464°N 106.764377°E / 15.059464; 106.764377 (Houayho HPP)1999152450793,53037
Houay La NgeHouay La-Nge15.774865°N 107.054896°E / 15.774865; 107.054896 (Houay La Nge HPP)202360290581791493.6
Houay Lamphan GnaiXekong15.356495°N 106.498949°E / 15.356495; 106.498949 (Houay Lamphan Gnai HPP)201584.84807774.51409
Houay PorHouay Por15.545605°N 106.256763°E / 15.545605; 106.256763 (Houay Por HPP)2018157560.76
Lower Houay Lam PhanhHouay Lamphan15.321515°N 106.630123°E / 15.321515; 106.630123 (Lower Houay Lam Phanh HPP)202215685552373.9
Nam AoNam Ao19.160876°N 103.283107°E / 19.160876; 103.283107 (Nam Ao HPP)2023159226130524.9
Nam BengNam Beng19.946436°N 101.237563°E / 19.946436; 101.237563 (Nam Beng HPP)20143614525.584.83,6110.7
Nam Che 1Nam Che19.054645°N 103.513536°E / 19.054645; 103.513536 (Nam Che 1 HPP)201916.82350
Nam Chien 1Nam Che19.145395°N 103.557259°E / 19.145395; 103.557259 (Nam Chien 1 HPP)2018104448.268.836714
Nam Houng 1Nam Houng19.189914°N 101.806322°E / 19.189914; 101.806322 (Nam Young 1 HPP)202315571.52
Nam Khan 2Nam Khan19.685364°N 102.369791°E / 19.685364; 102.369791 (Nam Khan 2 HPP)201513055816040530.5
Nam Khan 3Nam Khan19.747016°N 102.222793°E / 19.747016; 102.222793 (Nam Khan 3 HPP)2016884807774.51409
Nam Kong 1Nam Kong14.546513°N 106.740933°E / 14.546513; 106.740933 (Nam Kong HPP 1)20211606498738667921.8
Nam Kong 2Nam Kong14.494672°N 106.856669°E / 14.494672; 106.856669 (Nam Kong HPP 2)2018662645021071.44.2
Nam Kong 3Nam Kong14.566338°N 106.912551°E / 14.566338; 106.912551 (Nam Kong 3 HPP)2021542046550047132
Nam LeukNam Leuk/Nam Ngum18.437406°N 102.94675°E / 18.437406; 102.94675 (Nam Leuk HPP)20006021551.580018517.2
Nam Lik 1Nam Lik18.619438°N 102.387252°E / 18.619438; 102.387252 (Nam Lik 1 HPP)20196425636.57222.3
Nam Lik 1-2Nam Lik18.793782°N 102.116714°E / 18.793782; 102.116714 (Nam Lik 1-2 HPP)20101004351033281124.4
Nam Mang 1Nam Mang18.53423°N 103.196286°E / 18.53423; 103.196286 (Nam Mang 1 HPP)2016642257028016.50.148
Nam Mang 3Nam Gnogn18.349383°N 102.765244°E / 18.349383; 102.765244 (Nam Mang 3 HPP)200440150281514910
Nam Ngiep 1Nam Ngiep18.645828°N 103.552329°E / 18.645828; 103.552329 (Nam Ngiep 1 HPP)20192721,5461675301,19267
Nam Ngiep 1 (DS)Nam Ngiep18.647966°N 103.571591°E / 18.647966; 103.571591 (Nam Ngiep 1 (DS) HPP)20191810520904.61.27
Nam Ngiep 2Nam Ngiep19.243328°N 103.283818°E / 19.243328; 103.283818 (Nam Ngiep 2 HPP)201518073270.5163
Nam Ngiep 2BNam Ngiep19.155918°N 103.346031°E / 19.155918; 103.346031 (Nam Ngiep 2B HPP)20151876
Nam Ngiep 3ANam Ngiep19.243546°N 103.283913°E / 19.243546; 103.283913 (Nam Ngiep 3A HPP)2014441443011013.851.8
Nam Ngum 1Nam Ngum18.531068°N 102.547577°E / 18.531068; 102.547577 (Nam Ngum 1 HPP)19713151,455704684,700370
Nam Ngum 2Nam Ngum18.755374°N 102.776476°E / 18.755374; 102.776476 (Nam Ngum 2 HPP)20116152,300181.54213,590122.2
Nam Ngum 5Nam Ngum19.356095°N 102.621196°E / 19.356095; 102.621196 (Nam Ngum 5 HPP)2012120507104.525831414.6
Nam Ou 1Nam Ou20.0883°N 102.265379°E / 20.0883; 102.265379 (Nam Ou 1 HPP)20191607106544289.19.56
Nam Ou 2Nam Ou20.411698°N 102.472817°E / 20.411698; 102.472817 (Nam Ou 2 HPP)201612054655352121.715.7
Nam Ou 3Nam Ou20.695251°N 102.665404°E / 20.695251; 102.665404 (Nam Ou 3 HPP)202015068572340168.613.26
Nam Ou 4Nam Ou21.120153°N 102.494173°E / 21.120153; 102.494173 (Nam Ou 4 HPP)2020116524473001249.37
Nam Ou 5Nam Ou21.411349°N 102.344263°E / 21.411349; 102.344263 (Nam Ou 5 HPP)20162401,0497433517.22
Nam Ou 6Nam Ou21.411349°N 102.344263°E / 21.411349; 102.344263 (Nam Ou 6 HPP)20161807398840917.01
Nam Ou 7Nam Ou22.07779°N 102.264436°E / 22.07779; 102.264436 (Nam Ou 7 HPP)20201908111478251,49438.16
Nam Pha GnaiNam Pha Gnai19.013318°N 102.264436°E / 19.013318; 102.264436 (Nam Pha Gnai HPP)201619.2130651481.5
Nam PhayNam Phay19.109357°N 102.757461°E / 19.109357; 102.757461 (Nam Phay HPP)201886419.518.92
Nam San 3ANam San19.129193°N 103.661752°E / 19.129193; 103.661752 (Nam San 3A HPP)201669278.4753501238.5
Nam San 3BNam San19.085633°N 103.619938°E / 19.085633; 103.619938 (Nam San 3B HPP)201545198
Nam Tha 1Nam Tha20.249467°N 100.892433°E / 20.249467; 100.892433 (Nam Tha 1 HPP)2018168759.493.7349.21,755113.9
Nam Tha Had MuakNam Tha20.24264°N 100.712302°E / 20.24264; 100.712302 (Nam Tha 1 HPP)202237.5102.67
Nam Theun 1Nam Theun18.356733°N 104.148017°E / 18.356733; 104.148017 (Nam Theun 1 HPP)20226502,5611777712,77293.6
Nam Theun 2Nam Theun/Xe Bangfai17.997353°N 104.952306°E / 17.997353; 104.952306 (Nam Theun 2 HPP)20101,0755,936483253,500450
Theun-HinbounNam Theun18.261005°N 104.562525°E / 18.261005; 104.562525 (Theun-Hinboun Hydropower Plant)19982201,645488101,30049
Theun-Hinboun Expansion ProjectNam Gnouang18.297248°N 104.636171°E / 18.297248; 104.636171 (Theun-Hinboun Expansion Project)20132221,395654802,45049
XayaburiMekong19.254006°N 101.813699°E / 19.254006; 101.813699 (Xayaburi HPP)20191,2856,035488101,30049
Xe Kaman 1Xe Kaman14.960724°N 107.156336°E / 14.960724; 107.156336 (Xe Kaman 1 HPP)20182901,0961201854,804149.8
Xe Kaman 3Xe Kaman15.425194°N 107.362611°E / 15.425194; 107.362611 (Xe Kaman 3 HPP)20142501,000102543141.55.2
Xe Kaman-SanxayXe Kaman14.888908°N 107.117133°E / 14.888908; 107.117133 (Xe Kaman-Sanxay HPP)201832131.2281801.76
Xe Lanong 1Xe Lanong16.356276°N 106.238749°E / 16.356276; 106.238749 (Xe Lanong 1 HPP)202070269.967.5302953
Xepian-XenamnoyXepian/Xenamnoy15.026115°N 106.627369°E / 15.026115; 106.627369 (Xepian-Xenamnoy HPP)20194271,788731,6001,04350.6
Xe Nam Noy - Xe KatamXenamnoi/Xekatam15.117928°N 106.616688°E / 15.117928; 106.616688 (Xepian-Xenamnoy HPP)201620.183
Xeset 1Xeset15.49200°N 106.27867°E / 15.49200; 106.27867 (Xeset 1 HPP)19944515418124
Xeset 2Xeset15.403775°N 106.280332°E / 15.403775; 106.280332 (Xeset 1 HPP)20097630926144
Xeset 3Xe Don15.342113°N 106.31115°E / 15.342113; 106.31115 (Xeset 3 HPP)20172380111.3
ChulabhornNam Phrom16.536267°N 101.650036°E / 16.536267; 101.650036 (Chulabhorn HPP)197240937070016531
Lam Ta KhongLam Ta Khong14.865175°N 101.560303°E / 14.865175; 101.560303 (Lam Ta Khong HPP)197450040040.325131037
Pak MunMun15.2818942°N 105.468058°E / 15.2818942; 105.468058 (Pak Mun HPP)199413628017300
SirindhornLam Dom Noi15.206339°N 105.429156°E / 15.206339; 105.429156 (Siridhorn HPP)19713686429401,967288
Ubol RatanaNam Pong16.775394°N 102.618325°E / 16.775394; 102.618325 (Ubol Ratana HPP)196625.25735.18852,559410
A LuoiA Sap16.197619°N 107.161897°E / 16.197619; 107.161897 (A Luoi HPP)201217068649.5208
Buon KuopSre Pok12.52504°N 107.925762°E / 12.52504; 107.925762 (Buon Kop HPP)20092801,455341,828375.57
Buon Tua SraSe San/Krong Po Ko12.282116°N 108.041299°E / 12.282116; 108.041299 (Buon Tua Srah HPP)200986359831,04178741
Dray Hlinh 2Sre Pok12.6757°N 107.903978°E / 12.6757; 107.903978 (Dray Hinh 2 HPP)20071685
Hòa PhúSre Pok12.64967°N 107.909128°E / 12.64967; 107.909128 (Hòa Phú HPP)20142913212384.551.6
Krông Nô 2Krong No12.254355°N 108.355469°E / 12.254355; 108.355469 (Krông Nô 2 HPP)2016301099.3
Krông Nô 3Krong No12.254355°N 108.355469°E / 12.254355; 108.355469 (Krông Nô 3 HPP)20161863.542260201.75
Plei KrongSe San/Krong Po Ko14.408227°N 107.862991°E / 14.408227; 107.862991 (Plei Krong HPP)2008100479657451,04953
Sesan 3Se San14.215816°N 107.722061°E / 14.215816; 107.722061 (Sesan 3 HPP)20062601,224796.4
Sesan 3ASe San14.106475°N 107.657753°E / 14.106475; 107.657753 (Sesan 3A HPP)200796
Sesan 4Se San13.968252°N 107.49516°E / 13.968252; 107.49516 (Sesan 4 HPP)20093606054
Sesan 4ASe San13.933374°N 107.46683°E / 13.933374; 107.46683 (Sesan 4 HPP)20093606054
Sre Pok 3Sre Pok12.752344°N 107.876769°E / 12.752344; 107.876769 (Sre Pok 3 HPP)200922052.5
Sre Pok 4Sre Pok12.807331°N 107.855308°E / 12.807331; 107.855308 (Sre Pok 4 HPP)2009600329.3155860114150
Sre Pok 4ASre Pok12.893464°N 107.812294°E / 12.893464; 107.812294 (Sre Pok 4A HPP)2014308.354
Upper KontumSe San/Dak Bla/Dak Ngh14.694291°N 108.229879°E / 14.694291; 108.229879 (Upper Kontum HPP)20112501,056.4733921747.08
Yali FallsSe San14.227481°N 107.829597°E / 14.227481; 107.829597 (Yali Falls HPP)20017203,658.6651,4601,07364.5
Yan-Tann-SienYan-Tann-Sien12.152824°N 108.37866°E / 12.152824; 108.37866 (Yan-Tann-Sien HPP)201019.579

Notes: COD = Commercial Operating Date

Hydropower infrastructure under construction in the Mekong River Basin

Table 3: Hydropower dams under construction in the Mekong River Basin (15 MW installed capacity and above)[29]

ProjectCountryRiverLocationCODInstalled capacity (MW)Mean Annual Energy (GWh)Height (m)Crest length (m)Total storage (million m3)Max reservoir area (km2)
Pursat 1Pursat12.285408°N 103.298828°E / 12.285408; 103.298828 (Pursat 1 Dam)2026803611006871,039
CharikouTsichu32.670005°N 96.561546°E / 32.670005; 96.561546 (Charikou Dam) ?54121.4198.48421
JiaobaDengqu29.579527°N 98.306028°E / 29.579527; 98.306028 (Jiaoba Dam) ?6050
Houay Kaouane20.06663°N 102.192339°E / 20.06663; 102.192339 (Houay Kaouane) ?24
Luang PrabangMekong20.06663°N 102.192339°E / 20.06663; 102.192339 (Luang Prabang Dam)20301,4606,500802751,589.572.39
Nam AngNam Ang15.122545°N 107.108512°E / 15.122545; 107.108512 (Nam Ang Dam)202431183.30.03
Nam EmounNam Emoun15.5743°N 106.969395°E / 15.5743; 106.969395 (Nam Emoun Dam)2025131.5460.59291270.070.16
Nam Hinboun 1Nam Hinboun17.728201°N 104.571382°E / 17.728201; 104.571382 (Nam Hinboun 1 Dam)20241579.743370
Nam Hinboun 2Nam Hinboun18.023739°N 104.425006°E / 18.023739; 104.425006 (Nam Hinboun 2 Dam) ?30155.2382.57
Nam NgaoNam Hinboun20.398288°N 100.431852°E / 20.398288; 100.431852 (Nam Ngao Dam) ?1581.169438.62.57
Nam Ngum 3Nam Ngum19.084097°N 102.878817°E / 19.084097; 102.878817 (Nam Ngum 3 Dam)20244802,3452203951,41127.51
Nam Ngum 4Nam Ngum19.453804°N 103.010325°E / 19.453804; 103.010325 (Nam Ngum 4 Dam)202424087274110
Nam Phan (Bolevan)Nam Phak15.075548°N 106.139196°E / 15.075548; 106.139196 (Nam Phan Dam)2025168788
Nam Pot 1Nam Pot19.15518°N 103.266356°E / 19.15518; 103.266356 (Nam Pot 1 Dam) ?20924.9
Xe Lanong 2Xe Lanong16.291893°N 106.517774°E / 16.291893; 106.517774 (Xe Lanong 2 Dam) ?3514355
Xekong A (DS)Xekong14.599171°N 106.554175°E / 14.599171; 106.554175 (Xekong A (DS))202586334.78.595.0325.4
Xekong 4B (DS)Xekong15.744284°N 106.748666°E / 15.744284; 106.748666 (Xekong 4B)20271758011171,004.722.4

Notes: COD = Commercial Operating Date

Environmental impacts of Mekong hydropower

The environmental impacts of Mekong hydropower development are generally well studied and understood. Some the key impacts of Mekong hydropower are as follows:

Hydrological impacts: about 75% of annual flows through the Mekong system occur between late June and early November,[30][31] which drives ecological productivity throughout the system.[32][33] This surge of water is known as the 'flood pulse' and dams (of all kinds) will contribute to its diminution. Wet season flows can be expected to reduce, while dry season flows can be expected to increase.[34] This has significant implications for the Mekong's ecology.

Fisheries impacts: the Mekong's fisheries are threatened in multiple ways, most importantly by dams and excessive fishing pressure.[35] Dams affect fisheries by:[36]

  • Acting as barriers to fish migration - either as fish try to migrate upstream to spawn; or for trapping fish fry or eggs as these travel downstream.
  • Interrupting natural flood cycles to which fish have evolved and adapted to over thousands of years.
  • Riverbed hardening. Dams typically release water in bursts, which removes smaller sediments like silt, sand, and gravel, as well as aquatic plants and animals and debris from vegetation. As a result, the bedrock below the dam becomes exposed and loses its value as a fish habitat.
  • Trapping sediment, a significant source of nutrition for fish.[37]
  • Altering water temperature. Water released from a dam is typically colder than prevailing temperatures downstream of the dam. This has a direct impact on fish habitats and populations.
  • Hydropeaking, which refers to the release of water from HPPs when demand is highest (usually during the day), and much smaller releases when demand is low. This also affects fisheries through the rapid alteration and high and low river flows. Globally, hydropeaking has been found to impact fish biodiversity, and fish community composition.[36][38][39]

The fisheries impact of all existing and planned mainstream dams will be most felt in Cambodia (which will experience three-quarters of the loss), while the balance will be experienced in Vietnam, Lao PDR and Thailand.[39] In terms of tonnages, this will represent a loss of between 580-750,000 Mt per year.[39]

In another study by the Mekong River Commission, fisheries assessments conducted in 2020 suggested that the annual finfish yield from the lower Mekong (i.e. those parts of the basin that fall within Cambodia, Laos, Thailand and Vietnam)) was between 1.51 to 1.71 million tonnes, while the harvest of other aquatic animals (OAAs) was approximately 443,000 tons. This is approximately 25-30% less than yield estimates conducted in 2000 and 2010. The estimated value of the fish catch varies from USD 7.13 billion to USD 8.37 billion annually. In addition, the estimated value of the OAA harvest is approximately USD 1.13 billion.[40]

Sediment impacts: in the Mekong, some 40% of the sediments that reach the Mekong Delta are derived from the Three Parallel Rivers area in Yunnan, while some 52% come from the Central Highlands of Vietnam.[41] The balance comes from those parts of the basin in northern Thailand, and the Tibetan gorges.[41][42] Sediment loads are lowest during the dry season and highest during the first months of the flood season, when loose sediments weathered during the dry season are washed into rivers.[41][43]

Although suspended sediment concentrations in the Mekong have been monitored since 1994, the ‘pre-disturbance’ sediment load is unknown. Nevertheless, studies can demonstrate very significant declines in the Mekong's sediment load since 2001. At Chiang Saen, sediment flows have decreased from about 85 million metric tonnes per year (Mt/yr) to 10.8 million Mt/yr, meaning that the sediment contributions from China to the Mekong mainstream has decreased to about 16% of all sediments in the Lower Mekong as compared to about 55% historically.[44] A similar trend is seen down-stream at Pakse, where average loads have decreased from 147 Mt/yr to 66 Mt/yr between 1994 and 2013.[44]

The declining sediment load has significant implications for the Mekong Delta, recharging sediments otherwise washed away by the sea, consumed by sea-level rise, or in combination with land subsidence. Studies of the possible long-term consequences of system-wide sediment reductions suggest that it is likely that nearly half of the Delta's land surface will be below sea level by 2100, with the remaining areas impacted by saline intrusion from the sea and frequent flooding.[42] Much of the Mekong's sediment decline is attributed to the 'trapping efficiency' of dams.[42][44][45][46]

Forest impacts: there is a two-way relationship between (reservoir) hydropower and deforestation in the catchments they draw on. In the absence of soil conservation measures, deforestation often contributes to increased erosion, which is then deposited in the reservoir, reducing reservoir capacity. The 1,570 MW Manwan HPP on the Mekong mainstream in China, for example, lost 21.5–22.8% of the total storage capacity to sediments in its first 11 years of operation.[47] But hydropower can also drive deforestation. Reservoirs need to be cleared of vegetation before filling, and given the size of some reservoirs, the area subjected to clearance can be considerable. The deforestation impact of reservoir clearance in the Mekong is unknown. In 2008, an estimated 60% of the timber harvested in Laos was approved under special quotas for hydroelectric and other infra-structure projects.[48] It has been estimated that hydropower development contributes to the loss of 13,100 ha of forest a year in Laos.[49] Over 2006/07, the Lao national timber quota was temporarily raised by 400,000 m3 to allow for logging specifically related to the development of the Nam Theun 2 HPP.[50] It has been argued that logging represents an additional motivation to hydropower development, and is frequently linked to corrupt actors.[51]

River connectivity: 'connectivity' refers to the degree to which matter and organisms can move among spatially defined units in a natural system. ‘River connectivity’ is typically described as lateral (between a river's main channel and its floodplains), longitudinal (between upstream areas in the river channel or catchment, and downstream ones), and vertical (within the water column, between upper water layers and lower ones.[52][53] River connectivity can be conceptualised as a continuum from 'fully connected' to 'disconnected'. River connectivity strongly influences the resistance and resilience of rivers to natural and human-induced disturbances.[53]

Dams interrupt connectivity, and so fish cannot swim upstream to spawn or breed; dams affect water quality in a variety of ways, altering upstream ecosystems so that they contrast starkly with downstream ones. Dam reservoirs are lacustrine (lake-like) environments unlike rapidly flowing waters downstream; upstream, the water is heavy with sediments, while downstream it is not; above the dam, the water is cold, while below it, it is warmer.

A 2014 study explores an HPP build-out of 81 proposed dams across the Mekong Basin.[54] If this were to occur, it would reduce the Mekong's connectivity to just 11% by 2022. This build-out – already well advanced – would make the Mekong one of the most heavily impounded rivers in the world.

Greenhouse gases: hydropower reservoirs do emit greenhouses gases (GHGs), although the volumes and types depend on the reservoir's latitude and age.[55] Young reservoirs tend to release larger amounts of GHGs than older ones due to the availability of decomposing vegetation and other organic matter soon after initial inundation; tropical reservoirs tend to release more than temperate ones due to higher rates of net primary production.[55][56]

In the Mekong, one study looked at 119 reservoirs across the basin, and found that these emit be-tween 0.2–1,994 kg  of CO2 per MWh over a 100 year lifetime with a median of 26 kg  of CO per MWh.[57] Hydropower reservoirs that also provided irrigation water (22) had generally higher emissions reaching over 22,000 kg  of CO2 per  MWh.[57] Yearly emissions ranged from 26 to 181,3 000 Mt of CO2 per year over a 100-year lifetime, with a median of 28,000 Mt of CO2 per year. Altogether, 82% of hydropower reservoirs (119) and 45% of reservoirs also providing irrigation (22) had emissions comparable to other renewable energy sources (<190 kg  CO2 per  MWh), while the rest had higher emissions equivalent to fossil fuel power plants (>380 kg  CO2 per  MWh).[57] These results, the study authors caution, are tentative and they suggest that hydropower in the Mekong Region cannot be considered categorically as low-emission energy. Instead, the GHG emissions of hydropower should be carefully considered case-by-case.[57]

Mekong hydropower and resettlement of affected communities

People are affected by hydropower in a diversity of ways. Most immediately are those displaced by an HPP (i.e. resettled due to the presence of the dam itself, its reservoir, and/or ancillary buildings and infrastructure). Then there are those who will be affected by fisheries and sediment losses, and/or losses arising due to hydrological changes. Such populations may be eligible for compensation. Finally, there are broader impacts, related to the ways in which hydropower affects national economies. This section focuses on involuntary displacement and resettlement due to hydropower in the Mekong.

Figures for the number of people displaced by hydropower development are scattered and not generally available. Where data are available, they are as follows:

Table 4: Resettlement of hydropower-displaced people in the Mekong River Basin[29]

ProjectCountryStatusNo. resettled
Battambang 1Commissioned4,350
Lower Sesan 2Commissioned4,809
Pursat 1Under construction1,436
DachaoshanCommissioned6,363
DahuaqiaoCommissioned4,061
GongguoqiaoCommissioned3,476
HuangdengCommissioned4,415
JinfengCommissioned126
JinghongCommissioned2,264
LidiCommissioned575
Lin ChangCommissioned69
ManwanCommissioned7,260
MiaoweiCommissioned11,036
NuozhaduCommissioned43,602
TuobaUnder construction5,951
WunonglongCommissioned1,268
XiaowanCommissioned38,646
Xu CunCommissioned400
Don SahongCommissioned66
Houay HoCommissioned3,000
Luang PrabangUnder construction12,966
Nam Hinboun 2Commissioned1,200
Nam Kong 1Commissioned1,612
Nam LeukCommissioned134
Nam Lik 1-2Commissioned3,127
Nam Mang 3Commissioned1,200
Nam Ngiep 2Commissioned407
Nam Ngum 1Commissioned3,242
Nam Ngum 2Commissioned6,234
Nam Ngum 3Under construction523
Nam Ou 1Commissioned3,080
Nam Ou 2Commissioned700
Nam Ou 3Commissioned560
Nam Ou 4Commissioned630
Nam Ou 5Commissioned910
Nam Ou 6Commissioned210
Nam Ou 7Commissioned490
Nam San 3AUnder construction2,832
Nam Tha 1Commissioned10,523
Nam Theun 1Commissioned2,623
Nam Theun 2Commissioned6,200
Theun-HinbounCommissioned4,367
Xe Bang Hieng 2Commissioned2,700
Xe Pian-Xe Nam NoyCommissioned800
Xe Pon 3Commissioned600
Xekong 3BCommissioned240
Xekong 4ACommissioned4,458
Xekong 5Commissioned440
Ubol RatanaCommissioned30,000
A LuoiCommissioned872
Buôn KốpCommissioned4,732
Buon Tua SrahCommissioned2,215
Dray Hinh 1Commissioned153
Plei KrongCommissioned6,239
Sesan 3ACommissioned665
Sesan 4Commissioned1,021
Sre Pok 3Commissioned9,279
Upper KontumCommissioned1,363
YaliCommissioned24,610

In 2011, it was estimated that hydropower development in Laos would result in the resettlement of between 100,000 and 280,000 people.[58] In 2019, the Lao Minister of Energy and Mines estimated that, up until that point, 60,000 people from 12,000 families from more than 200 villages across Laos had been resettled to make way for power projects.[59] Similar estimates are not available for other parts of the Mekong River Basin.

See also

References

  1. "Mekong Mainstream Dams". International Rivers. Retrieved 2017-09-09.
  2. Mekong River Commission (2010). "State of the Basin Report, 2010" (PDF). MRC, Vientiane, Laos.
  3. J. Dore; Y. Xiaogang; K. Yuk-shing (2007). "China's energy reforms and hydropower expansion in Yunnan". In L. Lebel; J. Dore; R. Daniel; Y.S. Koma (eds.). Democratizing Water Governance in the Mekong Region. Chiang Mai: Silkworm Books. pp. 55–92. ISBN 978-9749511251.
  4. CGIAR Challenge Program on Water and Food. "CPWF Mekong". Archived from the original on April 28, 2012. Retrieved May 19, 2012.
  5. "Thousands Call for Regional Governments to Save the Mekong". International Rivers. Retrieved 2017-09-09.
  6. "A Dangerous Trajectory for the Mekong River". International Rivers. Retrieved 2017-09-09.
  7. Yeophantong, Pichamon (2014). "China's Lancang Dam Cascade and Transnational Activism in the Mekong Region: Who's Got the Power?". Asian Survey. 54 (4): 700–24. doi:10.1525/as.2014.54.4.700.
  8. Hennig, Thomas; Wang, Wenling; Magee, Darrin; He, Damming (2016). "Yunnan's Fast-Paced Large Hydropower Development: A Powershed-Based Approach to Critically Assessing Generation and Consumption Paradigms". Water. 8 (10): 476. doi:10.3390/w8100476. ISSN 2073-4441.
  9. Magee, Darrin (2006). "Powershed Politics: Yunnan Hydropower under Great Western Development". The China Quarterly. 185 (2006): 23–41. doi:10.1017/S0305741006000038. S2CID 154714463.
  10. Tilt, Brian (2015). Dams and development in China: the moral economy of water and power. New York: Colombia University Press. ISBN 978-0-231-17010-9.
  11. Liu, Shuangquan; Davidson, Michael (2021). China trading power: improving environmental and economic efficiency of Yunnan's electricity market (PDF) (Report). Environment and Natural Resources Program, Belfer Center for Science and International Affairs, Harvard Kennedy School. Retrieved February 8, 2024.
  12. Cheng, Chuntian; Chen, Fu; Li, Gang; Ristić, Bora; Mirchi, Ali; Qiyu, Tu; Madani, Kaveh (2018). "Reform and renewables in China: The architecture of Yunnan's hydropower dominated electricity market". Renewable and Sustainable Energy Reviews. 94 (2018): 682–693. Bibcode:2018RSERv..94..682C. doi:10.1016/j.rser.2018.06.033. S2CID 117337384.
  13. "Laos: electricity exports". Retrieved February 8, 2024.
  14. BOL (2023). Annual Economic Report 2022 (PDF) (Report). Bank of the Lao PDR. Retrieved January 12, 2024.
  15. "Department of Investment Promotion, Ministry of Planning and Investment (Lao PDR) Statistics". Retrieved 28 January 2024.
  16. Future Forum, Cambodia (April 2021). Chinese State-Owned Enterprises and Infrastructure Development in Cambodia: The Tatay River Hydropower Dam Project (PDF) (Report). BRI Monitor. Retrieved February 10, 2024.
  17. Siciliano, Giuseppina; Urban, Frauke; Tan-Mullins, May; Lonn, Pichdara; Kim, Sour (2016). "The Political Ecology of Chinese Large Dams in Cambodia: Implications, Challenges and Lessons Learnt from the Kamchay Dam". Water. 8 (9): 405. doi:10.3390/w8090405.
  18. "Hydropower Lower Sesan II". Retrieved 8 February 2024.
  19. "Cambodian PM Affirms Ban on Mekong Hydropower Projects". The Diplomat. December 1, 2023.
  20. Thul, Prak Chan (8 January 2020). "Don Sahong hydropower dam in Laos connects to Cambodian grid". Reuters. Retrieved 10 February 2024.
  21. Molle, François; Floch, Philippe (2008). "Megaprojects and Social and Environmental Changes: The Case of the Thai 'Water Grid'". AMBIO: A Journal of the Human Environment. 37 (3): 199–204. doi:10.1579/0044-7447(2008)37[199:MASAEC]2.0.CO;2. PMID 18595275. S2CID 31229220.
  22. Wangkiat, Paritta (8 May 2016). "Downstream countries concerned over water diversion". Bangkok Post. Retrieved 10 February 2024.
  23. Lan, Mai (6 June 2016). "Diverting the Mekong River into Thailand: The Khong-Loei-Chi-Mun project". Mekong Commons. Retrieved 10 February 2024.
  24. Simpson, Adam (2007). "The environment – energy security nexus: critical analysis of an energy 'love triangle' in Southeast Asia". Third World Quarterly. 28 (3): 539–554. doi:10.1080/01436590701192710. S2CID 154819073.
  25. Kirchherr, Julian; Pomun, Teerapong; Walton, Matthew J. (2016). "Mapping the Social Impacts of 'Damocles Projects': The Case of Thailand's (as yet Unbuilt) Kaeng Suea Ten Dam". Journal of International Development. 30 (3): 474–492. doi:10.1002/jid.3246.
  26. IFC (2018). Strategic Environmental Assessment of the Myanmar Hydropower Sector - Final Report (Report). International Finance Corporation. Retrieved February 10, 2024.
  27. ICEM (2010). Strategic Environmental Impact Assessment for Hydropower on the Mekong Mainstream - Final Report (PDF) (Report). Mekong River Commission. Retrieved February 8, 2024.
  28. HDR; DHI (2015). Study on the Impacts of Mainstream Hydropower on the Mekong River (PDF) (Report). Ministry of Natural Resources and the Environment (Vietnam). Retrieved February 8, 2024.
  29. "MERFI, 2024. Dataset on the Dams of the Greater Mekong". Bangkok: Mekong Region Futures Institute. Retrieved 2024-04-04.
  30. Piman, Thanapon; Cochrane, Thomas A.; Arias, Maricio E.; Green, Anthony; Dat, N.D. (1999). "Assessment of Flow Changes from Hydropower Development and Operations in Sekong, Sesan, and Srepok Rivers of the Mekong Basin". Journal of Water Resources Planning and Management. 139 (6): 723–732. doi:10.1061/(ASCE)WR.1943-5452.0000286.
  31. MRC (2005). Overview of the Hydrology of the Mekong Basin (PDF) (Report). Mekong River Commission. Retrieved 2024-02-12.
  32. Campbell, Ian C. (2009). "Introduction". In Campbell, Ian C. (ed.). The Mekong: biophysical environment of an international river basin. Amsterdam: Academic Press. pp. 1–11. ISBN 978-0-12-374026-7.
  33. Stone, Richard (August 12, 1999). "Mayhem on the Mekong". Science. 333 (6044): 814–818. doi:10.1126/science.333.6044.814. PMID 21835993.
  34. Hecht, Jory S.; Lacombe, Guillaume; Arias, Mauricio E.; Dang, Thanh Duc; Piman, Thanapon (2019). "Hydropower dams of the Mekong River basin: A review of their hydrological impacts". Journal of Hydrology. 568 (2019): 285–300. Bibcode:2019JHyd..568..285H. doi:10.1016/j.jhydrol.2018.10.045. S2CID 134742210.
  35. Ngor, Peng Bun; McCann, Kevin S.; Grenouillet, Gaël; So, Nam; McMeans, Bailey C.; Fraser, Evan; Lek, Sovan (2018). "Evidence of indiscriminate fishing effects in one of the world's largest inland fisheries". Scientific Reports. 8 (1): 8947. Bibcode:2018NatSR...8.8947N. doi:10.1038/s41598-018-27340-1. PMC 5997758. PMID 29895943.
  36. Pukinskis, Ilse; Geheb, Kim (2012). "The Impacts of Dams on the Fisheries of the Mekong". CGSpace. Vientiane: WLE Greater Mekong. Retrieved 2024-02-12.
  37. Baran, Eric; Guerin, Eric; Nasielski, Joshua (2015). Fish, sediment and dams in the Mekong (PDF) (Report). Penang: WorldFish and WLE Greater Mekong. Retrieved 2024-02-12.
  38. World Commission on Dams (2000). Dams and development - a new framework for decision-making. The Report of the World Commission on Dams (PDF). London: Earthscan. ISBN 9781853837982. Retrieved 12 February 2024.
  39. Yoshida, Yuichiro; Lee, Han Soo; Trung, Bui Huy; Tran, Hoang-Dung; Lall, Marian Keshlav; Kakar, Kifayatullah; Xuan, Tran Dung (2020). "Impacts of Mainstream Hydropower Dams on Fisheries and Agriculture in Lower Mekong Basin". Sustainability. 12 (6): 2408. doi:10.3390/su12062408.
  40. MRC (2020). Assessment of fisheries yield in the lower Mekong River Basin 2020 (PDF) (Report). Vientiane: Mekong River Commission. Retrieved 2024-02-12.
  41. MRC (2010). State of the Basin Report 2010 (PDF) (Report). Vientiane: Mekong River Commission. Retrieved 2024-02-13.
  42. Kondolf, George M.; Rubin, Zan K.; Minear, J. Toby (2014). "Dams on the Mekong: Cumulative sediment starvation". Environmental Management. 50 (6): 5158–5169. Bibcode:2014WRR....50.5158K. doi:10.1002/2013WR014651.
  43. Kummu, Matti; Varis, Olli (2007). "Sediment-related impacts due to upstream reservoir trapping, the Lower Mekong River". Geomorphology. 85 (3–4): 275–293. Bibcode:2007Geomo..85..275K. doi:10.1016/j.geomorph.2006.03.024.
  44. MRC (2019). State of the Basin Report 2018 (PDF) (Report). Vientiane: Mekong River Commission. Retrieved 2024-02-14.
  45. Allison, Mead; Nittrouer, Charles; Ogston, Andrea; Mullarney, Julia; Nguyen, Thanh (2017). "Sedimentation and Survival of the Mekong Delta: A Case Study of Decreased Sediment Supply and Accelerating Rates of Relative Sea Level Rise" (PDF). Oceanography. 30 (3): 98–109. doi:10.5670/oceanog.2017.318.
  46. Piman, Thanapon; Shrestha, Manish (2017). Case study on sediment in the Mekong River Basin: Current state and future trends (PDF) (Report). Stockholm: Stockholm Environment Institute. Retrieved 2024-02-14.
  47. Fu, K.D.; He, D.M.; Lu, X.X. (2008). "Sedimentation in the Manwan reservoir in the Upper Mekong and its downstream impacts". Quaternary International. 186 (1): 91–99. Bibcode:2008QuInt.186...91F. doi:10.1016/j.quaint.2007.09.041.
  48. PROFOR (2011). Improving Forest Governance in the Mekong Region: Options for Regional Activities in Sup-port of National Programs - Volume 1 (PDF) (Report). Washington D.C.: Program on Forests. Retrieved 2024-02-15.
  49. Thomas, Ian Lloyd (2015). Drivers of Deforestation in the Greater Mekong Subregion: Laos Country Report (PDF) (Report). USAID Lowering Emissions in Asia’s Forests (USAID LEAF) and the Food and Agriculture Organization. Retrieved 2024-02-15.
  50. Tong, Pei Sin (2009). Lao People's Democratic Republic Forestry Outlook Study (PDF) (Report). Rome: Food and Agriculture Organization. Retrieved 2024-02-15.
  51. Sopera, Danzig (2022). Corruption and water governance in the Mekong River Basin (PDF) (Report). U4 Issue 2022:12. Bergen: U4 Anti-Corruption Research Centre, Chr. Michelsen Institute. Retrieved 2024-02-15.
  52. Seliger, Carina; Zeiringer, Bernhard (2009). "River Connectivity, Habitat Fragmentation and Related Restoration Measures". In Schmutz, Stefan; Sendzimir, Jan (eds.). Riverine ecosystem management: science for Governing towards a sustainable future (PDF). Cham: SpringerOpen. pp. 171–186. doi:10.1007/978-3-319-73250-3. ISBN 978-3-319-73250-3. S2CID 24785869.
  53. Wohl, Ellen (June 15, 2017). "Connectivity in rivers". Progress in Physical Geography: Earth and Environment. 41 (3): 345–362. Bibcode:2017PrPG...41..345W. doi:10.1177/0309133317714972. S2CID 133801720.
  54. Grill, Günter; Ouellet Dallaire, Camille; Fluet Chouinard, Etienne; Sindorf, Nikolai; Lehner, Berhard (2014). "Development of new indicators to evaluate river fragmentation and flow regulation at large scales: A case study for the Mekong River Basin". Ecological Indicators. 45 (2014): 148–159. Bibcode:2014EcInd..45..148G. doi:10.1016/j.ecolind.2014.03.026.
  55. Deemer, Bridget R.; Harrison, John A.; Li, Siyue; Beaulieu, Jake J.; DelSontro, Tonya; Barros, Nathan; Bezerra-Neto, José F.; Power, Stephen M.; dos Santos, Marco A.; Vonk, J. Arie (2016). "Greenhouse Gas Emissions from Reservoir Water Surfaces: A New Global Synthesis". BioScience. 66 (11): 949–964. doi:10.1093/biosci/biw117. PMC 7425809. PMID 32801383.
  56. Yan, Xingcheng; Thieu, Vincent; Garnier, Josette (2020). "Long-Term Evolution of Greenhouse Gas Emissions From Global Reservoirs". Front. Environ. Sci. 9 (2021): 2408. doi:10.3389/fenvs.2021.705477.
  57. Räsänen, Timo; Varis, Olli; Scherer, Laura; Kummu, Matti (2018). "Greenhouse gas emissions of hydropower in the Mekong River Basin". Environ. Res. Lett. 13 (2018): 034030. Bibcode:2018ERL....13c4030R. doi:10.1088/1748-9326/aaa817. hdl:1887/68808.
  58. Fenton, Nina; Lindelow, Magnus; Heinimann, Andreas; Thomas, Ian (2011). The socio-geography of mining and hydro in Lao PDR: Analysis Combining GIS Information with Socioeconomic Data (PDF) (Report). Washington D.C.: World Bank. Retrieved 2024-02-17.
  59. Vientiane Times (2019-03-29). "12,000 Lao families relocated for hydropower projects". Vientiane Times. Vientiane. Retrieved 2024-02-18.
This article is issued from Wikipedia. The text is licensed under Creative Commons - Attribution - Sharealike. Additional terms may apply for the media files.